October progress billing match
Invoices20
Not matched20
Matches0
Differs0
In payment data0
10/27 · Bluejay Painting LLC

INV 26-1018

To: Ridgeline Builders

From: Bluejay Painting LLC

Site: Harborside expansion

Progress (cum.): 30%

Amount: $5,400

Lines: Exterior walls $3,780 / Steel members $1,620

10/27 · Oakline Doors & Hardware

Progress billing statement

Ridgeline Builders from Oakline Doors & Hardware

Project: Maple Court Apartments, new build

Order no. PO-26-0448

ItemPreviousThis periodTo date
Progress10%20%30%
Amount$3,900$7,800$11,700

Billed this period: $7,800

BreakdownAmount
Steel doors$4,680
Wood doors$3,120
10/28 · Crestline Electric Co.

PROGRESS BILLING INVOICE

Bill to: Ridgeline Builders

From: Crestline Electric Co. Date: October 31, 2026

Project: Maple Court Apartments, new build

PO number: PO-26-0412

Contract amount: $70,000

Percent complete to date: 50%

Earned to date: $35,000

Less previous billings: $24,500

Amount due this period: $12,360

BreakdownAmount
Main power distribution$6,300
Lighting and outlets$4,200
Added: relocate entrance lights (3)$1,860
10/28 · Sunrise Waterproofing

Sunrise Waterproofing

To the project team, Ridgeline Builders

Please find our progress billing for October.

Job: Maple Court, waterproofing

Progress: 30% this month (80% to date)

Amount: $6,600

Breakdown: Roof membrane $4,950; Balcony waterproofing $1,650

Thank you for your business.

10/28 · Clearwater Glass

Clearwater Glass

To the project team, Ridgeline Builders

Please find our progress billing for October.

Job: Greenfield gym, glazing

Progress: 50% this month (50% to date)

Amount: $4,300

Breakdown: Glass fabrication $2,150; Glazing $2,150

Thank you for your business.

10/29 · Northstar Steel Works

PROGRESS BILLING INVOICE

Bill to: Ridgeline Builders

From: Northstar Steel Works Date: October 31, 2026

Project: Harborside Logistics Center expansion

PO number: PO-26-0427

Contract amount: $124,000

Percent complete to date: 60%

Earned to date: $74,400

Less previous billings: $37,200

Amount due this period: $37,200

BreakdownAmount
Steel fabrication$24,180
Steel erection$13,020
10/29 · Greenleaf HVAC

INV 26-1060

To: Ridgeline Builders

From: Greenleaf HVAC

Site: Maple Court

Progress (cum.): 45%

Amount: $10,350

Lines: Equipment setting $5,690 / Refrigerant and ductwork $4,660

10/29 · Crestline Electric Co.

PROGRESS BILLING INVOICE

Bill to: Ridgeline Builders

From: Crestline Electric Co. Date: October 31, 2026

Project: Harborside Logistics Center expansion

PO number: PO-26-0415

Contract amount: $48,000

Percent complete to date: 40%

Earned to date: $19,200

Less previous billings: $9,600

Amount due this period: $9,600

BreakdownAmount
Main power distribution$5,760
Lighting and outlets$3,840
10/30 · Summit Scaffolding

INV 26-1074

To: Ridgeline Builders

From: Summit Scaffolding

Site: Greenfield gym

Progress (cum.): 100%

Amount: $4,900

Lines: Scaffold erection $3,430 / Netting and protection $1,470

10/30 · Cornerstone Interiors Inc.

Progress billing statement

Ridgeline Builders from Cornerstone Interiors Inc.

Project: Maple Court Apartments, new build

Order no. PO-26-0430

ItemPreviousThis periodTo date
Progress20%15%35%
Amount$0$22,050$22,050

Billed this period: $22,050

BreakdownAmount
Metal stud framing$8,820
Drywall$7,720
Floor finishes$5,510
10/30 · Fieldstone Sitework

INV 26-1088

To: Ridgeline Builders

From: Fieldstone Sitework

Site: Harborside expansion

Progress (cum.): 20%

Amount: $6,600

Lines: Paving $3,960 / Planting $2,640

10/30 · Eastwood Plumbing & Mechanical

Eastwood Plumbing & Mechanical

To the project team, Ridgeline Builders

Please find our progress billing for October.

Job: Maple Court, plumbing

Progress: 20% this month (45% to date)

Amount: $11,200

Breakdown: Water and hot water piping $5,600; Drain piping $3,360; Fixture installation $2,240

Thank you for your business.

10/31 · Stonegate Plastering

Stonegate Plastering

To the project team, Ridgeline Builders

Please find our progress billing for October.

Job: Greenfield gym, plastering

Progress: 40% this month (60% to date)

Amount: $5,800

Breakdown: Floor screed $3,480; Wall base coat $2,320

Thank you for your business.

10/31 · Liftway Elevator Co.

PROGRESS BILLING INVOICE

Bill to: Ridgeline Builders

From: Liftway Elevator Co. Date: October 31, 2026

Project: Maple Court Apartments, new build

PO number: PO-26-0469

Contract amount: $98,000

Percent complete to date: 40%

Earned to date: $39,200

Less previous billings: $29,400

Amount due this period: $9,800

BreakdownAmount
Elevator fabrication$6,860
Installation$2,940
10/31 · Ironwood Foundations

PROGRESS BILLING INVOICE

Bill to: Ridgeline Builders

From: Ironwood Foundations Date: October 31, 2026

Project: Harborside Logistics Center expansion

PO number: PO-26-0436

Contract amount: $86,000

Percent complete to date: 100%

Earned to date: $86,000

Less previous billings: $60,200

Amount due this period: $25,800

BreakdownAmount
Piling$15,480
Foundation concrete$10,320
10/31 · Summit Scaffolding

INV 26-1123

To: Ridgeline Builders

From: Summit Scaffolding

Site: Harborside expansion

Progress (cum.): 80%

Amount: $5,200

Lines: Scaffold erection $3,640 / Netting and protection $1,560

10/31 · Bluejay Painting LLC

INV 26-1130

To: Ridgeline Builders

From: Bluejay Painting LLC

Site: Greenfield gym

Progress (cum.): 70%

Amount: $4,050

Lines: Exterior walls $2,840 / Steel members $1,210

11/01 · Redline Demolition

Progress billing statement

Ridgeline Builders from Redline Demolition

Project: Greenfield Elementary gym renovation

Order no. PO-26-0463

ItemPreviousThis periodTo date
Progress60%40%100%
Amount$12,600$8,400$21,000

Billed this period: $8,400

BreakdownAmount
Interior strip-out$3,360
Structural demolition$3,360
Debris disposal$1,680
11/01 · Greenleaf HVAC

INV 26-1144

To: Ridgeline Builders

From: Greenleaf HVAC

Site: Greenfield gym

Progress (cum.): 60%

Amount: $9,600

Lines: Equipment setting $5,280 / Refrigerant and ductwork $4,320

11/01 · Brightview Windows

PROGRESS BILLING INVOICE

Bill to: Ridgeline Builders

From: Brightview Windows Date: October 31, 2026

Project: Maple Court Apartments, new build

PO number: PO-26-0457

Contract amount: $44,000

Percent complete to date: 50%

Earned to date: $22,000

Less previous billings: $11,000

Amount due this period: $11,000

BreakdownAmount
Aluminum frame fabrication$6,600
Window installation$4,400