Ironwood Foundations

Not matched

PROGRESS BILLING INVOICE

Bill to: Ridgeline Builders

From: Ironwood Foundations Date: October 31, 2026

Project: Harborside Logistics Center expansion

PO number: PO-26-0436

Contract amount: $86,000

Percent complete to date: 100%

Earned to date: $86,000

Less previous billings: $60,200

Amount due this period: $25,800

BreakdownAmount
Piling$15,480
Foundation concrete$10,320