Crestline Electric Co.

Not matched

PROGRESS BILLING INVOICE

Bill to: Ridgeline Builders

From: Crestline Electric Co. Date: October 31, 2026

Project: Harborside Logistics Center expansion

PO number: PO-26-0415

Contract amount: $48,000

Percent complete to date: 40%

Earned to date: $19,200

Less previous billings: $9,600

Amount due this period: $9,600

BreakdownAmount
Main power distribution$5,760
Lighting and outlets$3,840