Ridgeline BuildersJob cost and payables Monday, November 2Accounts · Nina

← Back to the match

Liftway Elevator Co.

Not matched

PROGRESS BILLING INVOICE

Bill to: Ridgeline Builders

From: Liftway Elevator Co. Date: October 31, 2026

Project: Maple Court Apartments, new build

PO number: PO-26-0469

Contract amount: $98,000

Percent complete to date: 40%

Earned to date: $39,200

Less previous billings: $29,400

Amount due this period: $9,800

BreakdownAmount
Elevator fabrication$6,860
Installation$2,940