PROGRESS BILLING INVOICE
Bill to: Ridgeline Builders
From: Liftway Elevator Co. Date: October 31, 2026
Project: Maple Court Apartments, new build
PO number: PO-26-0469
Contract amount: $98,000
Percent complete to date: 40%
Earned to date: $39,200
Less previous billings: $29,400
Amount due this period: $9,800
| Breakdown | Amount |
| Elevator fabrication | $6,860 |
| Installation | $2,940 |